Evaluation of Extension of time Claims November 21, 2024
EXTENSION OF CONTRACT PERIOD IN CONSTRUCTION PROJECTS
- Extension of construction
period of any project will result in additional cost to both the Employer and
the Contractor (except the Engineer – most benefitted party).
- The Evaluation of EOT will determine, who will bear those additional costs.
- The Contractor has to bear all the additional costs, if the project is extended due to the delays within the contr0l of Contractor (Avoidable delays)
- In case of the delays within the contr0l of the Employer (Unavoidable delays) the Employer has to bear all the additional costs.
- In case of Neutral Event
(Weather) both parties has to share the additional cost.
1) Requirement of
EOT Clause in the Conditions of Contract
All types of Conditions of Contract have EOT Clause, (Clause 44
in FIDIC – 1987, Clause 8.4 in FIDIC 1999).
E.O.T. clause is required to cater for the delay caused by the
Employer/the Engineer or neither party
to the Contract
Without E.O.T. Clause, the completion of works delayed by the
Employer/Engineer or by a Neutral event will relieve the Contractor from his
liability to pay liquidated damages and the time for completion may become at
large.
In the absence of Contractual power, the Engineer could not
extend the time for completion.
Failure by the Engineer to properly exercise the power to extend
time, will relieve the Contractor from his liability to pay liquidated damages
and the time for completion may become ‘at large’.
Under no circumstances the Contractor will be entitled to
receive financial compensation for his delays.
If the party, who has been damaged, fails to mitigate damages,
it may not be able to recover those damages which could have been mitigated.
Thus it is important for the contractor to make reasonable efforts to minimize
the damages it sustains as a result of a delay
2) Types of
Delays in Construction Projects
Construction
Delays can be divided into 03 categories
Employers
delays
Preventive or
unavoidable delays –Refer Clause 8.4 of
FIDIC - 1999
- Land Acquisition
- Utility Diversion
- Design, Quantity and other variation
- Main Contractor not having received instructions, drawings,
details or levels from the Engineer in due time necessary for which he applied
in writing.
- Delays due to different site conditions – Depth of peat layers
in STDP
- Employers delays (Cont’d)
- Delay on the part of nominated subcontractors or nominated
suppliers which the Main Contractor has taken all practicable steps to avoid or
reduce.
- Delay on the part of artists, tradesmen or others engaged by the
Employer.
- Opening up for inspection of any work covered up for additional
testing, inspection by the Engineer of
any of the work, materials or goods.
- Unforeseen shortage of labour & materials .
- Discovery of antiquities.
- Force Majeure – Clause 19.1to 19.4 – FIDIC 1999
- Loss of efficiency, out
of Sequence work caused by Disruption ( Protests, court proceeding, etc)
- Contractor’s
Delays - Culpable
/Avoidable delays
- Slow progress due to
inadequate resources or low productivity than planned or caused by both
- Strikes
- Defective Work/Quality
Issues– additional resources need for correction and affect of this work on
critical path
- Suspension of work due to inadequate safety
- Neutral Events
- Inclement Weather or any
other reasons in the Condition of Contract
- Rainfall shall exceeds the 98 percentile value of the daily
rainfall for that calendar month
- Work shall be planned to be carried out on the particular day
- Delay of that work should
affect the completion of the project
3) Entitlement
of additional cost in EOT claims:
If project
delays:
- Only due to the Employers
delays - The Contractor is entitled for EOT and to claim additional cost incurred by him – in some events with
reasonable profit
- Only due to Neutral Events
- Both Contractor and the Employer
has to shear additional cost
- Only due to the
Contractor’s delays -The Contractor has to pay LD- Additional cost of the
Employer
- In case of concurrent
delays, the Engineer has to determine
depending on particular situation.
4) Additional
cost due to extension of the Project Period
- The Employers Costs is called Liquidated Damages (LD)
LD - The economic
loss to the Employer due to delay
of completion. Very critical in private sector projects,
since the employer has to pay interest
for bank loans without expected income
- Supervision and other direct OHs of the Employer.
- Loss of revenue due to delayed use, interest expenses during delayed period
- Any other reasonably foreseeable damages the owner may have
incurred including lost of profit from a business.
- The Contractor’s Costs
- Indirect costs – include
job site overhead (e.g. project supervision costs), extended general conditions
or extended or unabsorbed overhead, job shack, portable toilet, telephone,
insurance, and job site power and water
- Direct cost - Equipment
rental costs and equipment ownership expenses, demobilization and
re-mobilization expenses, increased (material escalation – if not paid
separately) material costs, etc
- home office overhead that
was incurred during the extended performance period
- lost productivity caused by
the delay
- interest on the claim, lost
profits on other jobs, etc
5) Evaluation
EOT Claim
Evaluation EOT
Claims include:
- The determining the period of extension
- The party or parties responsible for the delays
- Additional cost entitlement of the parties
The EOT
determinations are very complicated due to following reasons:
- Always there will be
concurrent delays of all types
- Different interpretation of
the Conditions of Contract by parties to the Contract
¢
Ambiguities,
contradictions, mistakes, etc in the contract documents will lead to different
interpretations and disputes (No contract document is perfect).
¢
Some contractors &
other parties use these conflicts for their benefit without considering
reasonableness & fairness and also assuming that the other party will
overlook those issues.
¢
When such disputes go
before Arbitrator/Courts, they look at practicality and reasonableness of the
issues, implied terms, in addition to
word to word interpretations of condition of contract.
Examples
A: BSL Project – giving responsibility of
utility shifting to the Contractor
B: Delay in getting GSMB and other license
- In EOT claims, the
Contractor will give priority for the delays of the Employer, since he can
recover his costs and if project will extended more, then he will go for
neutral delays
¢
The Contractor will hide
all avoidable delays even there is possibility that those delays could be
critical, since he will not get EOT for those delays.
¢
When the Engineer will
evaluate the Contractor’s Claim, they rarely try to find whether there are any
other delays of the Contract affecting
completion of the Project.
¢
Unless the Employer has
people who could scrutinize these claims and point out these delays, the
Contractors will always get their EOT claims with additional cost.
Examples
A: STDP – ADB Section – Hiding delays due to
Bridge repairs
B: KG BSL Project –Hiding Delays of drainage
defects
C: STDP – JICA Pack 2 - Hiding Delays of SGT –
highlighting only Rock qty increase by 200%. In the Engineer’s evaluation he
used original Construction program for evaluation – which will not indicate any
of the Contractor’s delays at the time of submitting EOT.
Determining EOT caused by Concurrent Delays
Delays going side
by side or running together at the same time are considered concurrent
delay.
There are 03
basic principles on dealing with concurrent
delays:
(1) The first in
line approach
(2) The
dominant cause approach
(3)
The apportionment approach
Each approach can
appear logical and correct in
appropriate circumstances but depend on view point of the interested party.
Examples 1.
Reimbursable = > Non – Reimbursable
The contractor
will argue “first in line” approach - The employer should reimburse addition
cost of the contractor for entire 15.
The Employer will
argue for apportionment approach – According to this approach, the Contactor
will be entitled for OH for 10 month period and the Contractor has to bear the
cost of balance 5 month period.
No LD for 15w, OH for 10w, No OH for 5w
But, most
reasonable argument in this case will be the first-in-line approach, since
delay due to weather would not have affected if there was no delay by the
employer. (We used same approval in the
evaluation of EOT in Works Division)
No LD for 15w, OH for 15w -
reasonable
Examples 2. Non – Reimbursable = > Reimbursable
The Employer prefer first in line
approach – As per this approach, the Contractor will not get for 1st
10 Weeks and get OH for the balance 5W
No. LD for 15w, No OH for 10w, OH for 5w
The Contractor will prefer
apportionment or the dominant approach
Dominant Approach
- No LD for 15w, OH for 10w, No OH for 5w
Apportionment Approach
- No LD for 15w, OH for 7.5w, No OH for 7.5w
Most reasonable approach will be
one of the last two approaches
Examples 3. Reimbursable = > Culpable
The Contractor will argue for first in line approach – request EOT of 15W, proposing that the Employer’s delay came first.
- No LD for 15w, OH for
15w
The Employer will go for
apportionment approach
- No LD for 2.5 w, OH for
7.5 w, LD for last 5W
usually in a dispute resolution the
decision will be as follows.
- No LD for 10w, OH for 10w, LD for last 5W
Examples 4. Culpable = > Reimbursable
The Contractor will request
- No LD for 15w, OH for 15w
But, usually the Contractor will
get
- OH for 10w, LD for last
5w
But this will depend on nature of
the Employer’s delay. If a VO for a new work is issued during the
first 5w of the Contractor’s delay, then the Contractor will be entitled to get
his OH for entire 15w. In such a situation the Contractor will argue that the
EOT due to Employer’s delay could not be avoided even if he completed his work
on time.
Examples 5. Non reimbursable = > Culpable
Usually
No LD for 10w and LD for last5w.
But there could be instances that
the Employer will argue that the Contractor’s delay could not be avoided, even
if the weather was perfect.
Examples 6. Culpable = > Non reimbursable
In this situation, the Employer’s
argument will be that the weather could not have affected the project, if the
Contractor completed project on time,
- LD for 15w
But, the Contractor will be
argue for 10w EOT for weather
- No OH, LD for 5w
But In similar situation, In court
case between Building Contractors Vs, Wolthom Holy Cross UDC (1952), the Judge granted EOT for the
neutral event in consideration of fairness.
6) Determining EOT caused by Concurrent Delays
From decisions given in some court
cases, it appears that the Contractor is entitled to cover his additional cost,
only when there is pure owner caused delay. And it is also clear that no
recovery can be had when concurrence delays can be shown.
In case of Concurrence
delays, which attributable to the Employer and the Contractor, the Court will
not generally enforce the Clause EOT or
LD.
However, there are cases, where the
court has attempted to apportion the damages.
7) Analyzing
Effect of Delays in Project
The construction program is used to
analyses as to whether the project will extend due to particular delay. The completion date of a project will be
extended only If:
a. The delayed activities are in the critical path
b. The delay in particular activity will affect resources
requirement of the Project (the Contractor need additional resources)
c. Instruction to increase resources more than what is allowed in
the Original schedule could be considered as instruction for Acceleration
The responsibility for preparation
of construction Program rest with the
contractor,
- But the Engineer
should review the program,
submitted by the Contractor and approve
it.
- If necessary the Engineer
should request clarification and advice the Contractor to make necessary
amendments, before approving it.
The Complete
Construction program (CP) should indicate:
- All activities of the
project,
- Duration, start & finish dates of activities
- Precedence (dependence)
between activities
- Resources available for the
project
- Resources allocated for
each activity
- Productivity of allocated
resources shall be as per acceptable Construction norms. However most of the norms could depends on
conditions of particular site, type and condition of the machines available for
the project, skill of the labour and operators available, etc.
- The program should be
resources driven - reducing/increasing
allocated resources should change duration of
the activity. These facilities
are available in both MS project and Primavera.
Common
Deficiencies in the Construction
Programs (CP)
- CP is not done by
experience programmer - Large projects have thousands of Activities. Input of
full time programming engineer with adequate experience in programming software
and construction work is required for preparation of CP and monitoring
- Most of the time the
Contractors are unable to achieve planned production rates, given in the
programs and regular updating and monitoring of production rates not done.
- Precedence of activities
incomplete
Problems in
Evaluation EOTs Using Incomplete/Defective Construction Programs
- will be difficulty to identify delays in critical activities,
actual requirement of resources, allocation of resources to critical
activities, etc until it is too late to
take corrective measures
- will result in arbitrary awarding of EOTs without proper
analysis.
- In case of concurrent delays the
Contractors will manipulate incomplete CP by allocating less resource to
those activities, which could become critical by the slightest Employer’s
delays.
Monitoring
Progress Using Construction Program
- The approved program should
be save as Baseline before updating the program by entering following actual
conditions
- Start & finish dates, duration
- Resources allocated for activities and available for
the project
- productivity
- The Engineer shall monitor
the actual conditions against planned and inform the Contractor to take
necessary precautions to improve the progress.
If these conditions are not monitored, the Contractor
will come up with different reasons for delay of activities at later stage of the project.
Who has right to use available float
in the Construction program
- In most of the dispute situation determination has been:
- The float belongs to neither party but is for use of both
parties
- Most of the cases it has been decided that the float belongs to
the party, who use it first.
Example: 1
- there is 15 day float in the program
- Experience two sequential delays of 10 days each – first 10 days
contractor delay, 2nd 10 days the Employer’s delay.
- In such situation the Contractor will be entitled for 05 days
EOT
Example 2
- The Contractor is 30 days ahead of the schedule expecting to
complete the Contract early and leave the site early. This will save his
overheads
- At the Final stage, the Employer issue a VO for additional work
and the Contractor will not be able to complete the job on expected date
Decision of
dispute;
- By the terms of contract, the Contractor has to complete the
scope by a given date, not required to remain on the jobsite until a given
date.
- In this situation, the Contractor will be entitled to fair and
reasonable compensation for the increase in indirect cost incurred plus profit on those cost.
Analyzing Effect of Delays in
Project
Monitoring progress
When the program is updated with
actual progress, it will show when the delay of activities will start affecting
the completion date. the Completion date will affect only if
- the critical path activities are delayed
- A non critical activity has become critical due to reduction of
float.
- Even though some activities have float, moving of that activity
forward due to delays will affect the resource requirement during the balance period of the project (will require
increasing of resources). If this happens due to
- Avoidable delay, it is
Contractors responsibility take mitigatory measures.
- Unavoidable delay the
Contractor will be entitled for EOT or acceleration cost.
If the activities are delayed due to avoidable reasons, the
Contractor will require to mobilize additional resources to complete the
remaining work within the balanced period.
The Contractor should show as to how he is going complete this work (
the additional resources he will
mobilize), when the CP is updated
Common
Problems observed in updating CP
- The contractor will always
try to hide culpable delays by allocating less resources to varied work or new
works and making that those activities come to
critical path, which is
difficult to prevent unless
there is close monitoring by the Engineer.
- Every effort shall be made
to minimize issuing variations at latter stage of the project.
- CPs are updated without
saving the baseline details of the
programs making it difficult to monitor where the delays have occurred
- When the programs were
updated the balance durations of the activities are reduced, without
considering resources required or technical possibility to complete the balance
volume of work within shorter period.
8) The Details
to be included in presenting EOT Claims:
a) Description of
the cause of delay.
b) The
contractual provision which is being relied upon.
c) The date when
the delay commenced and the period of delay.
d) The date of
notice of delay.
e) A summary of
records and particulars relied upon.
f) A description
of the event and effects on progress.
g) A diagrammatic
illustration showing the status of the program, progress and current completion
date prior to the commencement of the delay.
9) Major
obstacles to EOT claim :
a) Late or lack
of notice from the Contractor.
b) Failure to
recognize delay that results in contemporary records not being kept.
c) Failure to
regularly update the program.
d) Poor
presentation of the claim to show how the progress of the work has been
delayed.
e) Insistence on the part of the Employer’s professional advisers, that unreasonably detailed critical path programs are essential in order to assess the effects of the delay.
10) Notice Requirements for Loss & Expense Claim
a) Some notice
requirements are condition precedent to the Contractor’s entitlement and
therefore the Contractor loses his right to claim if he fails to comply with
such a notice requirement.
b) Failure to
give notice in accordance with the contract may bar or severely prejudice a
claim for additional payment
c) If specific
notice provisions are inserted, the Contractor must comply with these
requirements
d) Advance
warning of the possibility of an increase in the contract price
Acceleration –
Action taken by the contractor in order
to speed up the progress on a job to accomplish early or to make up for the
lost time
Three types of
Acceleration
1-Voluntarily – the Contractor at
his own initiative, makes effort to
- Overcome his own delays
- Complete earlier than planned
Additional cost
will be borne by the Contractor
2-As per the instruction of the
owner – directed or ordered
If any additional
cost involved that has to be borne by the Contractor
3-Constructive – the Contractor
finish the job as planed, where unavoidable ( Employer’s) delays has occurred,
but no EOT has given - no directive of
the Employer required
If the Contractor want to recover any
additional cost – he has to submit notice of claim
CONCLUSION
- If the Employer is unable to handover certain section of the
site at the commencement of the project, always the schedule of handing over of
possession of site shall be included in to the bidding documents or to the
Contract documents in the negotiation stage.
This will make the Contractor to consider those delays in the
preparation of the CP.
Popular Articles
Evaluation of Extension of time Claims
This article is talking about the evaluation of Extension of time Claims
PMP and CAPM
This article's purpose is to explain what is the difference between PMP and CAPM
Claims Management in Construction: Essential Elements and Procedures for Success
This article is going to argue the following: Claim Essential Elements - Contractual Procedure - Entitlement
AACE Certified Cost Professional (CCP) Exam: Your Ultimate Guide!
CCP exam provider is AACE International (Association for the Advancement of Cost Engineering)